A 2013 plan is finalised!

We can now announce the agenda for Gagarin Square's progress in 2013.

1)       To attain planning permission this summer;

2)        To remove 55 Southwark Street down to its basement during early July;

3)       To clear the site of all concrete and Victorian brick foundations from mid  July to mid August;

4)       To commence perimeter piling no later than September 1;

5)       To expedite archaeological investigations after piling during November 2013 – February 2014.